Before you book a new office or a new home in Maharashtra, the project's page on the MahaRERA website is the first public record you can check yourself. This guide explains what the law asks a promoter to put on that page, how often it has to be updated, and how to turn that into a checklist you can use before you pay a booking amount.

Throughout, "the Act says", "the Rules say" or "the order says" means the text of that document says so. "Practical tip" means a suggestion of ours that goes beyond the words of the law.

The three documents behind this guide are:

01Does this apply to offices and shops?

Yes. The Act defines an "apartment" to include a "block, chamber, dwelling unit, flat, office, showroom, shop, godown, premises" and similar units, used "for any residential or commercial use". So a new office or shop in a registered project is covered in the same way as a flat. The checks below work for both.

02Step 1: Is the project registered at all?

The Act says (Section 3(1)) that no promoter shall "advertise, market, book, sell or offer for sale, or invite persons to purchase" any plot, apartment or building in a real estate project in a planning area without first registering the project with the Authority.

Three points in Section 3 matter to a buyer:

  • Phases are separate projects. The Explanation to Section 3 says that where a project is developed in phases, "every such phase shall be considered a stand alone real estate project", registered separately. The building or wing you are buying in must be covered by the registration you check.
  • Some projects are exempt. Section 3(2) lists cases where registration is not required, including where the land does not exceed five hundred square meters or the apartments do not exceed eight, inclusive of all phases. A proviso allows the "appropriate Government" to reduce that threshold.
  • The registration has a validity period. Under Section 5(3) it is valid for the period the promoter declared for completing the project or phase. Section 6 allows the Authority to extend it, and the Rules (rule 6(a)) say the Authority issues a Registration Certificate with a project registration number in Form "C".

Practical tip: Note the registration number from the advertisement, then find the same number on the MahaRERA website yourself. Check that the promoter's name, the project name, the address and the phase or wing all match what you are being sold. If the project says it is exempt, ask the promoter in writing which part of Section 3(2) it relies on.

03Step 2: What the promoter must disclose on the project page

When a promoter applies, Section 4(2) of the Act lists the documents it must enclose. Once registration is granted, Section 5 gives the promoter a login to the Authority's website "to create his web page and to fill therein the details of the proposed project".

The Act says (Section 11(1)) that the promoter shall create that web page and "enter all details of the proposed project as provided under sub-section (2) of section 4, in all the fields as provided, for public viewing". Section 4(2) includes, among other things:

  • the promoter's enterprise details, and a brief of projects launched in the past five years, with their status, delays and pending cases (clauses (a) and (b));
  • authenticated copies of approvals and the commencement certificate, for each phase where applicable (clause (c));
  • the sanctioned plan, layout plan and specifications (clause (d));
  • the plan of development works and facilities, including fire fighting, drinking water, emergency evacuation and renewable energy (clause (e));
  • location details with boundaries and the latitude and longitude of the end points (clause (f));
  • the proforma allotment letter, agreement for sale and conveyance deed (clause (g));
  • the number, type and carpet area of apartments, and the number and areas of garages (clauses (h) and (i));
  • the names and addresses of real estate agents, contractors, architect and structural engineer (clauses (j) and (k));
  • a declaration supported by an affidavit on title, encumbrances, the time period for completion, and the deposit of seventy per cent. of amounts realised from allottees in a separate account in a scheduled bank (clause (l)).

The Rules add (rule 3(2)) further items, including the promoter's PAN, a legal title report authenticated by a practising advocate, any development or collaboration agreement with the landowner, encumbrances and sub-judice proceedings on the land, the sanctioned and proposed FSI, buildings, wings and floors, and the number of covered parking spaces. Where the proposed FSI, buildings or floors differ from what is sanctioned, rule 3(2)(f) says the later sanction "shall be uploaded on the website of the Authority by the promoter from time to time".

The Rules say (rule 20) that the Authority shall make the promoters' disclosures available on its website, with listed exceptions, and that those exceptions do not apply to the details a promoter must enter on its own web page under Section 11(1). Rule 20(2) also says the Authority "shall ensure that such information is updated at the interval of every quarter".

Practical tip: The agreement for sale you are later asked to sign should match the proforma agreement uploaded under Section 4(2)(g). Download the uploaded version early and compare the two before you pay anything substantial.

04Step 3: The updates the promoter must keep making

The Act says (Section 11(1)(b) to (e)) the web page must carry, "quarterly up-to-date", the number and types of apartments or plots booked, the number of garages booked, the approvals taken and those pending after the commencement certificate, and the status of the project.

Order No. 33/2022 groups the promoter's updates into categories and sets their frequency:

CategoryWhat the order requiresWhen
Quarterly updatesQuarterly Progress Report (QPR): incremental changes in building plan approvals (if any), physical progress, booking status of plots/apartments/units and of garages; a self-certification if no money was withdrawn from the designated bank account that quarter, also stating the amount depositedWithin 20 days of the quarter end (20th of July, October, January and April)
Annual updatesAnnual Statement of Accounts in Form 5Within six months after the end of every financial year
Annual updatesForm 2A: Quality Assurance CertificateWithin three months after the end of every financial year
Withdrawal formsCopies of Form 1, Form 2 and Form 3, the three certificates given to the bank for each withdrawal from the designated accountAs and when submitted to the bank
Other regular updatesChanges in the encumbrances report and updated CERSAI reports; changes in project professionals (architect, engineer, chartered accountant, real estate agents); formation of the legal entity (society, co-op etc.); litigation detailsAs and when they change; the legal entity within three months of the majority of allottees having booked
CompletionForm 4, the architect's certificate of completion with the OC number, and the occupancy certificates issuedOn completion
ConveyanceDisclosure signed by the promoter and the association of allottees confirming conveyance3 months after OC

The order says most of these updates "shall be made immediately available for public viewing", and that homebuyers "can track and evaluate the progress, of their real estate project, online on regular basis".

What changed from Order No. 18/2021. The earlier order set the QPR deadline at 7 days from the quarter end and put more items into the quarterly report. Order No. 33/2022 says Order No. 18/2021 "stands substituted with this order", so the 20-day timeline and the categories above are the ones in force under the orders we hold.

Practical tip: The quarter-by-quarter record is often more useful than any single figure. A project page that has stopped receiving QPRs, or that shows little physical progress over several quarters, is a reason to ask the promoter direct questions before booking.

05Step 4: The advertisement itself

The Act says (Section 11(2)) the promoter's advertisement or prospectus must mention prominently the Authority's website address and the project registration number. MahaRERA's later orders 46/2023, 46A/2023, 46B/2023 and 46C/2025 also require a project QR code in promotions, with rules on size, colour and placement. We cover those in the MahaRERA advertisement and QR code checklist.

06Checklist: what to look for on the project's MahaRERA page

Every item below is something the Act, the Rules or Order No. 33/2022 requires the promoter to disclose or update. The pinpoint is in brackets.

  1. 1Registration number and certificate that match the ad, the promoter and the project name (Act s.11(1)(a), s.11(2); Rules rule 6(a)).
  2. 2Validity period of the registration and any extension (Act s.5(3), s.6).
  3. 3The right phase or wing, since each phase is registered on its own (Act s.3, Explanation).
  4. 4Approvals and commencement certificate for the phase you are buying in (Act s.4(2)(c)).
  5. 5Sanctioned plan, layout and specifications, and, where they differ from the proposal, the later sanctioned FSI, buildings, wings or floors (Act s.4(2)(d); Rules rule 3(2)(f)).
  6. 6Carpet area and unit types for sale, and garage numbers and areas (Act s.4(2)(h), (i)).
  7. 7Title and encumbrances: the title report, any development agreement, and the encumbrance details (Act s.4(2)(l); Rules rule 3(2)(c) to (e)).
    • Check for changes in the encumbrances report and updated CERSAI reports (Order 33/2022).
  8. 8Completion date declared by the promoter (Act s.4(2)(l)(C)).
  9. 9Proforma agreement for sale, allotment letter and conveyance deed (Act s.4(2)(g)).
  10. 10Promoter's track record: projects launched in the past five years, with delays and pending cases (Act s.4(2)(b)).
  11. 11Project professionals and agents, and any later changes (Act s.4(2)(j), (k); Order 33/2022).
  12. 12Quarterly Progress Reports for each quarter: approvals, physical progress, bookings of units and garages (Act s.11(1)(b) to (e); Order 33/2022).
  13. 13Designated account: Form 1, 2 and 3 for each withdrawal, or the quarterly self-certification of no withdrawal (Order 33/2022).
  14. 14Annual filings: Form 5 Annual Statement of Accounts and Form 2A Quality Assurance Certificate (Order 33/2022).
  15. 15Litigation details (Order 33/2022).
  16. 16For a completed project: Form 4, the occupancy certificate and, later, the conveyance disclosure (Order 33/2022).

07Practical tips beyond the law

  • Keep a dated copy. Save or print the pages you relied on, with the date. Pages are updated, and you may later need to show what was disclosed when you booked.
  • Compare, don't just tick. The value of the page is in matching it with the brochure, the sample flat or office, the allotment letter and the agreement.
  • Ask in writing. If an item is missing or out of date, put the question to the promoter by email and keep the reply.
  • Check the Authority's other records. Section 34 of the Act requires MahaRERA to keep, for public viewing, records of registered projects and a database of promoters whose registration has been revoked or who have been penalised, with reasons.

08What this guide does not cover

This guide does not cover complaints, refunds, interest or possession remedies, and it does not describe the MahaRERA website's menus, which can change. It is based on the orders listed above. MahaRERA may have issued later orders or circulars on project updates; check the Authority's website for the current position before you rely on any point.