You booked a new flat or office in a registered project, and the possession date in your agreement for sale has come and gone. This guide sets out what the Real Estate (Regulation and Development) Act, 2016 and the Maharashtra Rules say about that, in their own words where it matters.

Throughout, "the Act says" or "the Rules say" means the text of the law says so. "Practical tip" means a suggestion of ours that goes beyond the text. No decided cases are covered, and nothing here predicts how a complaint will turn out.

01Does this apply to an office as well as a flat?

The Act says: the remedies below are written for an "allottee" of an "apartment, plot or building". The Act's definition of "apartment" (section 2(e)) begins:

"apartment" whether called block, chamber, dwelling unit, flat, office, showroom, shop, godown, premises, suit, tenement, unit or by any other name

It covers "residential or commercial use". An "allottee" (section 2(d)) "does not include a person to whom such plot, apartment or building... is given on rent". So a new office bought from a promoter is treated like a flat; a tenant is outside the definition.

02Where the possession date comes from

The Act says: the agreement for sale must specify, among other things, "the date on which the possession of the apartment, plot or building is to be handed over" and "the rates of interest payable by the promoter to the allottee and the allottee to the promoter in case of default" (section 13(2)).

The model agreement says: the model form of agreement for sale that MahaRERA asks promoters to follow (Annexure 'A' under rule 10, reproduced with Order 60/2024) has a blank date to fill in at clause 6, which begins "The Promoter shall give possession of the Apartment to the Allottee on or before". Clause 2.2 states: "Time is essence for the Promoter as well as the Allottee."

Practical tip: the date that matters is the one in your registered agreement. For what to check at booking stage, see booking a new flat: allotment letter and agreement checks.

03Your two choices under section 18

Section 18(1) applies if the promoter "fails to complete or is unable to give possession of an apartment, plot or building":

  • (a) "in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein"; or
  • (b) "due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason".

The section then gives the allottee two different routes.

Route 1: withdraw and take a refund

The Act says: the promoter "shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act".

Section 19(4) states the same entitlement from the allottee's side: to "claim the refund of amount paid along with interest" and "compensation".

Route 2: stay in the project and receive interest

The Act says (proviso to section 18(1)):

Provided that where an allottee does not intend to withdraw from the project, he shall be paid, by the promoter, interest for every month of delay, till the handing over of the possession, at such rate as may be prescribed.

Model agreement clause 4.1 repeats this: interest "as specified in the Rule, on all the amounts paid by the Allottee, for every month of delay, till the handing over of the possession".

Practical tip: one route ends the purchase, the other keeps it alive. The Act leaves the choice to the allottee ("in case the allottee wishes to withdraw"). Weigh it with your adviser and your home-loan lender before you write to the promoter.

04The interest rate: what the Maharashtra Rules prescribe

The Rules say: rule 18 of the Maharashtra Real Estate (Regulation and Development) (Registration of real estate projects, Registration of real estate agents, rates of interest and disclosures on website) Rules, 2017 reads:

The rate of interest payable by the promoters to the allottees or by the allottees to the promoters, as the case may be, shall be the State Bank of India highest Marginal Cost of Lending Rate plus two percent:

Its proviso adds that if the SBI Marginal Cost of Lending Rate "is not in use it would be replaced by such benchmark lending rates which the State Bank of India may fix from time to time for lending to the general public".

The Rules give a formula, not a number: the figure depends on SBI's lending rate, which is not in the Rules, so this guide states no current percentage.

The Act says: the same rate works in both directions. Section 2(za) defines "interest" and explains that "the rate of interest chargeable from the allottee by the promoter, in case of default, shall be equal to the rate of interest which the promoter shall be liable to pay the allottee, in case of default". It also sets the period. Interest payable by the promoter runs "from the date the promoter received the amount or any part thereof till the date the amount or part thereof and interest thereon is refunded".

The 2019 amendment to these Rules (6 June 2019) does not change rule 18 or rule 19.

05How quickly a refund is to be paid

The Rules say (rule 19):

The refund of any amount which is payable by the promoters to allottees along with the applicable interest and compensation, if any, under the Act or the Rules and Regulations, shall be made by the Promoter to the allottee within thirty days from the date on which such refund along with applicable Interest and Compensation, becomes due and payable to the allottee:

The proviso requires every such instance to "be reported by the concerned promoters within thirty days to the Authority". The rule does not say how the date a refund "becomes due and payable" is fixed.

06Compensation is separate from interest

The Act says: section 18(3) adds that a promoter who fails to discharge "any other obligations" under the Act, the rules, the regulations or the agreement for sale "shall be liable to pay such compensation to the allottees, in the manner as provided under this Act".

The manner is in sections 71 and 72. Under section 71(1), "for the purpose of adjudging compensation under sections 12, 14, 18 and section 19", the Authority appoints an adjudicating officer, a judicial officer "who is or has been a District Judge". After an inquiry, the officer "may direct to pay such compensation or interest, as the case any be, as he thinks fit" (section 71(3), spelling as printed). Section 71(2) asks for disposal "within a period of sixty days from the date of receipt of the application", or reasons in writing.

Section 72 lists what the adjudicating officer "shall have due regard to" when fixing compensation or interest:

  1. 1"the amount of disproportionate gain or unfair advantage, wherever quantifiable, made as a result of the default";
  2. 2"the amount of loss caused as a result of the default";
  3. 3"the repetitive nature of the default";
  4. 4"such other factors which the adjudicating officer considers necessary to the case in furtherance of justice".

Practical tip: the Act fixes no compensation amount. Any loss you want considered, such as rent paid while waiting, needs documents behind it. Keep receipts and correspondence in date order.

07Who you complain to

The Act says (section 31(1)): "Any aggrieved person may file a complaint with the Authority or the adjudicating officer, as the case may be". The Explanation says "person" includes "the association of allottees or any voluntary consumer association".

Section 31(2) leaves "the form, manner and fees for filing complaint" to regulations made by the Authority. Those regulations are not covered here; check the current procedure and fees with MahaRERA.

Section 40(1) provides that interest, penalty or compensation imposed on a promoter and not paid "shall be recoverable... as an arrears of land revenue". Section 88 says the Act is "in addition to, and not in derogation of, the provisions of any other law for the time being in force".

08When can a promoter get more time?

The Act says: section 6 lets the Authority extend a project's registration on the promoter's application "due to force majeure". It defines force majeure as "a case of war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the real estate project". A proviso allows extension "in reasonable circumstances, without default on the part of the promoter", not exceeding one year "in aggregate".

The Rules say: rule 6(a) states that the registration validity period "shall exclude such period where actual work could not be carried by the promoter as per sanctioned plan due to specific stay or injunction orders relating to the real estate project" from a court, tribunal or authority. The 2019 amendment deleted the words that had also allowed "such mitigating circumstances as may be decided by the Authority".

The model agreement says (clause 6 proviso): the promoter "shall be entitled to reasonable extension of time for giving delivery" if completion is delayed on account of "(i) war, civil commotion or act of God ; (ii) any notice, order, rule, notification of the Government and/or other public or competent authority/court".

These provisions deal with the registration period and the contract. The texts used here do not say how an extension of registration affects a claim under section 18.

Practical tip: compare the completion date on the project's MahaRERA page with the possession date in your agreement. They need not be the same.

09Once possession is offered

The model agreement says:

  • Clause 7.1: the promoter "shall offer the possession to the Allottee in writing within 7 days of receiving the occupancy certificate of the Project".
  • Clause 7.2: "The Allottee shall take possession of the Apartment within 15 days of the written notice".

The Act says (section 19(10)): "Every allottee shall take physical possession of the apartment, plot or building as the case may be, within a period of two months of the occupancy certificate issued".

Practical tip: the Act and the model clauses use different time frames. Read your own agreement, and take advice before letting a possession offer backed by an occupancy certificate lapse.

10A short checklist

  1. 1Find the possession date and the interest clause in your registered agreement for sale.
  2. 2Decide, with advice, whether you intend to withdraw (refund) or stay (monthly interest). The Act treats these differently.
  3. 3Collect dated proof of every payment; under section 2(za), interest runs from the date the promoter received each amount.
  4. 4Check the project's MahaRERA page for extensions and the declared completion date.
  5. 5Keep evidence of any loss you want considered as compensation (section 72).
  6. 6Confirm the complaint form, procedure and fees with MahaRERA before filing.