01What this covers

This guide sets out the permissions MIDC's own regulations require to build a factory on an MIDC plot, in the order they arise, from the building plan to the occupancy certificate.

The main source is the Comprehensive Development Control and Promotion Regulations for MIDC (CDCPR). The Urban Development Department sanctioned it by notification No. TPB-4322/314/CR-25/2022/UD-11 dated 5 July 2023, and it came into force on publication in the Gazette on 13 July 2023. A corrigendum dated 21 May 2025 amended some provisions; where it touches anything cited here, this guide says so. Page numbers below are Gazette page numbers.

02The sequence of approvals

  1. 1Building permission and commencement certificate. Your registered architect, town planner or licensed engineer applies to MIDC with plans, ownership documents, any NOCs from other departments, and the scrutiny fee. Construction cannot start before this permission.
  2. 2Fire scrutiny and provisional fire NOC. MIDC's provisional fire NOC is applied for together with the building plan, in the same online application. For a "special building", the Chief Fire Officer (CFO) of MIDC must clear the scheme before permission is issued.
  3. 3Display board on site as soon as permission is granted (Reg. 2.8.2, p. 54).
  4. 4Plinth intimation. When work reaches plinth level, the owner informs MIDC in the prescribed form. Work then continues.
  5. 5Revised permission if you intend a substantial deviation from the sanctioned plans.
  6. 6Completion certificate. The supervising architect or engineer submits it with the completed plans and other certificates. For a special building, the final fire NOC from MIDC's CFO goes with it.
  7. 7Occupancy certificate (OC), full or part, issued by MIDC after inspection.

03Is a factory a "special building"?

A lot of the fire requirements turn on this definition, so check it first. Under Reg. 1.3(111)(xiv), a "Special Building" includes:

  • any building 24 m or more in height, and any hazardous building more than 15 m high;
  • any building used for hotel, educational, institutional, business, mercantile, industrial, storage, hazardous or mixed occupancies, where the floor area is more than 500 sqm on any one or more floors;
  • any building with two or more basements, or one basement of more than 500 sqm.

A note to the definition carves out certain mixed-occupancy buildings up to 24 m (built-up area up to 750 sqm on any floor, sprinklers provided, travel distance maintained), "subject to fire NOC" (Gazette p. 30).

What this means in practice: on the regulation's wording, most factory and warehouse buildings with a floor above 500 sqm fall in the special-building category. Your architect should confirm this for your design.

04What each regulation says

StageWhat is requiredRegulation / page
Permission is mandatoryNo erection, re-erection, alteration or demolition of a building without a building permit / development permission / commencement certificate from MIDCCDCPR Reg. 2.1.1, p. 39
ApplicationNotice in the prescribed form (Appendix A1/A2) through a registered architect, town planner or licensed engineer/supervisor, with the scrutiny-fee receipt, plans and statements; plans may be submitted electronicallyReg. 2.2.1, p. 42
Ownership documentsIncluding a copy of the lease agreement, as applicable, and a measurement plan from Land Records or a demarcation plan issued by MIDCReg. 2.2.3, p. 43
Building plans1:100 floor plans, sections and elevations, with FSI calculations, use of every part, parking and loading/unloading spacesReg. 2.2.7, p. 45
Special buildings: extra detailsFire-appliance access, staircases, fire lift, fire alarm, static water tank, sprinklers/wet risers as required by MIDC's CFO, structural certificate, and clearance from MIDC's CFOReg. 2.2.8, pp. 45–46
NOCs from other departmentsWhere applicable, NOCs from authorities such as the Civil Aviation Authority, Directorate of Industries, Maharashtra Pollution Control Board, Inspectorate of Boilers and Smoke Nuisance, DISH and PESO accompany the applicationReg. 2.2.12, p. 47, as amended by the 2025 corrigendum, entry 13 (pp. 25–26)
Scrutiny feeFor building construction: Rs. 10 per sqm of built-up area, subject to a maximum of Rs. 3,00,000, "subject to orders of the Authority from time to time"Reg. 2.2.13, Table 2A, p. 47
Development chargesPayable under section 124A of the MRTP Act before the permission is issuedReg. 2.2.14, p. 47
Structural stabilityFor special buildings, a licensed structural engineer's stability certificate accompanies the applicationReg. 2.2.16, p. 49
DecisionMIDC sanctions, refuses or sanctions with modifications; special buildings only after the CFO's clearance. After objections are complied with, MIDC is to grant or refuse within 60 days of resubmissionReg. 2.6.1, pp. 51–52
Deemed permissionIf MIDC does not communicate a decision within 60 days of the notice (with fees), the notice is deemed sanctioned, subject to the provisos in the regulationReg. 2.6.2, p. 52
ValidityCommencement certificate valid for 4 years in aggregate, renewed every year until work commences; no renewal needed once work starts within validityReg. 2.7.1, p. 52
PlinthIntimation in Appendix F, certified by the architect/engineer, after work reaches plinth levelReg. 2.8.3, p. 54
DeviationSubstantial deviations need MIDC's sanction on a revised plan; unapproved work is unauthorisedReg. 2.8.4, p. 54
CompletionCompletion certificate (Appendix G) with three sets of completed plans, lift certificate and structural stability certificate where necessary; final fire NOC for special buildingsReg. 2.9, p. 54
OccupancyOC (Appendix H) after inspection, or refusal with reasons (Appendix I)Reg. 2.10, pp. 54–55
Part occupancyPossible on request before the whole work is complete, with an indemnity in Appendix JReg. 2.11, p. 55

05Fire NOC

Provisional fire NOC

MIDC's procedure document, Procedure for Issuance of Provisional Fire No-Objection Certificate, says the following (p. 1):

  • One combined online application goes through MIDC's single-window portal (BPAMS) for the building plan, provisional fire NOC, temporary water connection and external drainage connection.
  • The application is forwarded automatically to the concerned Fire Officer. It is scrutinised by AutoDCR software and verified by the Fire Officer.
  • The Fire Officer issues a demand letter for the Fire Protection Fund Fees, based on total built-up area and building height. Payment is online.
  • After scrutiny and payment, the provisional NOC is issued online for download.

The listed documents include:

  • a note on the plant's activity with a process flow chart, and the raw materials and finished goods with their quantities and storage places marked on the block plan;
  • copies of approvals from bodies such as the Chief Controller of Explosives, Excise, MPCB, DISH or FDA, where the materials require them;
  • an NOC from the Civil Aviation Authority for high-rise buildings near an airport;
  • for expansions, the existing BCC/part BCC, DCC and approved drawings;
  • the architect's certificate that the plans comply with MIDC's D.C. Rules and Parts 3 and 4 of NBC-2005.

The document carries a fee table (pp. 2–7). It sets rates per sqm with minimum amounts, varying by MIDC zone (A, B, C under the "Group Scheme 1993"), building class (for example Industrial G-1 to G-3, Storage H, Hazardous J), height and built-up area. The document has no date, so this guide does not quote its figures. Rely on the demand letter issued for your proposal.

Final fire NOC

The CDCPR requires the CFO's final fire NOC with the completion certificate for special buildings. It also requires the CFO's clearance on fire protection before an OC is issued (Regs. 2.9 and 2.10, pp. 54–55). None of the sources listed with this article sets out the procedure or documents for the final fire NOC.

06Completion and occupancy

The regulation says (Reg. 2.9, p. 54): the owner, through the architect or engineer who supervised construction, submits the completion certificate in Appendix G. The Appendix G form (p. 243) also has the owner state that premium charges payable in instalments under Reg. 2.2.15 are fully paid.

The regulation says (Reg. 2.10, pp. 54–55):

  • MIDC inspects and, if there is no deviation from the sanctioned plans, issues the OC. Otherwise it refuses, giving reasons.
  • If MIDC does not do so within 21 days of receiving the completion certificate, the work is deemed approved for occupation, provided it conforms to the sanctioned plans.
  • An eligible applicant may request a deemed OC, which MIDC is to issue within 15 days of the application.
  • For special buildings, the OC follows the CFO's clearance.

The regulation says (Reg. 2.11, p. 55): a part OC may be issued for a building or part of one before the entire work is complete. It requires adequate safety precautions and an indemnity in Appendix J.

MIDC's Citizen's Charter (Marathi, dated 9 January 2018). Service 3 covers the occupancy / part occupancy certificate, भोगवटा / भाग भोगवटा प्रमाणपत्र, for a building on a developed plot. Its document list (PDF pp. 30–31, printed pp. 28–29) includes:

  • the online OC/part OC application;
  • the architect's building completion certificate and the structural engineer's stability certificate;
  • the plumber's certificate for the water connection and drainage;
  • MIDC's final fire NOC;
  • a no-dues certificate from MIDC's water billing section;
  • MPCB Consent to Operate, FDA approval and factory registration under the Factories Act, where applicable;
  • a Rs. 500 stamp-paper indemnity bond for a part OC;
  • for low-risk buildings, a site inspection report by the plot holder; for medium-risk buildings, one by the architect/structural engineer and a licensed fire agency.

It gives the service time as 15 days, citing circular C-55146 dated 13/07/2017.

Caution: this charter predates the CDCPR. It refers to forms of the 2009 regulations (Form 8 and Form 14), which the CDCPR replaced (Reg. 1.2, p. 17). Treat its list as an indication of what MIDC has asked for, not as the current requirement.

07Practical tips

These are practical suggestions, not requirements of the regulations.

  • Settle the special-building question at concept stage. It decides whether CFO scrutiny, the extra fire details in Reg. 2.2.8, a structural stability certificate with the application and a final fire NOC apply.
  • Collect process information early. The fire NOC asks for raw materials, finished goods, quantities and storage locations. Fix these with your process team before the architect finalises drawings.
  • Keep deviations under control. Changes inside a unit's internal layout that do not breach FSI or other rules are not unauthorised and go on the completion plans (Reg. 2.8.4). Anything substantial needs a revised permission first.
  • Plan the OC file in parallel with construction. Consents such as MPCB Consent to Operate and the factory licence come from other authorities on their own timelines.

08What the sources don't cover

  • MIDC's current BPAMS workflow: screens, document checklist and timelines. A 13 January 2026 public notice says BPAMS has incorporated the CDCPR and that a revision has begun; it invited architects' and engineers' suggestions within seven days. The revised process itself is not in these sources. See the BPAMS revision notice.
  • The procedure, documents and fees for the final fire NOC.
  • A current, dated fire fee schedule. The provisional fire NOC document is undated and refers to NBC-2005, while the CDCPR refers to NBC 2016.
  • A post-2023 Citizen's Charter with current OC and building-permission service times.
  • Consents under other laws (MPCB, Factories Act, boilers, explosives), beyond the fact that the CDCPR and the charter list them as attachments.
  • Plot-level conditions in your lease deed or allotment letter. The CDCPR requires an NOC where a proposal deviates from lease conditions or uses more FSI than the lease deed mentions (Reg. 2.2.3(viii), p. 43).

The full regulation is on MIDC's site: CDCPR 2023 (Gazette) and the 2025 corrigendum.