A shed that looks right on a brochure can still fail your operation: racking that does not fit under the trusses, trucks that cannot turn in the yard, a sanctioned load that covers the lights but not your machines. These problems are cheap to find before you sign and expensive afterwards.
This checklist is written for the plant head, logistics manager or project team walking a shed or warehouse in Chakan, Talegaon, Ranjangaon, Khandala, Satara or anywhere else. It is framed as questions to ask and things to measure. It does not set out legal standards: the rules that apply depend on the plot, the authority and your activity, and must be confirmed for each property.
01Before the visit
- 1Write down your own requirement first: racking or process layout, heaviest load on the floor, largest vehicle that will come in, number of docks needed at peak, power and water demand, and headcount per shift.
- 2Ask the owner or broker for the building drawings (site plan, floor plan, sections) and a copy of the title and approval documents in advance, so the visit is spent checking rather than collecting.
- 3Take a laser distance meter, a camera and someone from your engineering or warehouse team.
02The building
Clear height
Measure the clear height to the lowest obstruction, not to the ridge: the underside of the truss, purlin, light fitting, sprinkler line or ventilator, whichever is lowest. Measure at the eaves and at the centre. Then check it against your racking height plus the clearance your racking supplier and fire consultant need. There is no universally "good" figure; confirm against your racking or process need.
Floor
- Ask for the design floor load in writing, with the structural engineer's drawing or certificate it comes from. A verbal figure is not enough.
- Ask what the floor was designed for: static racking loads, point loads from rack legs, forklift or reach-truck wheel loads, or heavy machinery with foundations.
- Look for cracks, settlement, uneven joints and patches. Ask whether the floor surface (trimix, epoxy, VDF or other) suits your material-handling equipment.
- If you will install heavy machines, ask whether separate foundations are allowed and who restores the floor at exit.
Column grid
Measure the spacing of columns in both directions and lay it over your racking and aisle plan. A grid that cuts across aisles can cost more storage positions than a slightly smaller shed with a clean grid.
Roof, light and ventilation
- Roof sheeting type, insulation, and any visible leaks or staining after rain.
- Natural light panels, ridge or turbo ventilators, and whether the shed gets hot by mid-afternoon (ask to visit at that time if heat matters for your product or workforce).
Cranes and gantry readiness
If you need an EOT crane, ask whether the columns and crane girders or brackets were designed for one, and for what capacity. Ask for the structural drawing. Adding a crane to a shed not designed for it usually means new columns.
03Docks, yard and access
Docks and levellers
- Number of docks, dock height, and whether levellers, shelters and dock lights are installed or only provided for.
- Docks on one side or both, and whether that fits your flow.
- Whether additional docks can be cut in later, and at whose cost.
Yard and truck turning
Walk the route your largest vehicle will take: gate, yard, reversing to the dock, and exit. Ask whether a full-length truck can turn without reversing onto the road, and where trucks will wait at peak. Check yard surfacing and how it holds up in the monsoon.
Access road
- Width and condition of the approach road; any low bridges, railway crossings, narrow village stretches or heavy-vehicle time restrictions.
- Whether the access is a public road, an MIDC road or a private easement. If private, ask for the document that grants the right of way.
04Services
Power
- Sanctioned load and contract demand on the current electricity bill, and the connection category.
- Transformer: whose it is, its rating, and its condition. Ask whether it is dedicated to this shed or shared.
- Whether the supply can be enhanced for your demand, who applies, and who pays for any new transformer or cabling.
- DG set provision and outage history (ask neighbouring units, not only the owner).
Water
Source (MIDC, gram panchayat, borewell or tanker), the sanctioned quantity if any, storage tanks, and recent bills. If your process needs water, confirm the supply before you design around it.
Drainage
Ask how storm water leaves the plot and look for signs of waterlogging in the yard or near the docks. Ask how sewage and any trade effluent are handled, and whether there is a connection to a common facility.
Fire-fighting provisions
- What is installed: hydrant system, sprinklers, fire alarm, extinguishers, fire water tank and pump room. Ask whether the pump is tested and when it was last serviced.
- Ask for the fire NOC and what occupancy, storage height and material class it was issued for. A NOC for general storage may not cover your goods or your racking height. Your fire consultant should confirm what your use needs.
05Approvals and documents to ask for
Ask for copies; check them with your advocate and consultants. These are questions, not a statement of what the law requires for your property.
- Title and ownership: who owns the land and building, and whether the person signing has the right to lease or sell. For leasehold plots, the lease deed from the land-owning authority.
- Building permission and occupancy certificate: the approved plans and the occupancy (or completion) certificate, and whether the built shed matches the approved plans. Ask about any extensions, mezzanines or sheds added later.
- Fire NOC: as above, for the actual occupancy and storage.
- Pollution control consent: where your activity needs consent from the Maharashtra Pollution Control Board (MPCB), ask whether the property has existing consent, for what activity, and whether you will need your own.
- MIDC plots: if the property is in an MIDC area, ask whether MIDC's permission for the transfer, sub-lease or change of use has been obtained or will be obtained, and at whose cost. Confirm which MIDC development control regulations apply to that specific plot.
- Dues: recent property tax, MIDC service charges where applicable, electricity and water bills, with no arrears.
- Encumbrances and disputes: mortgages, pending litigation, or claims by other parties.
For reference, the MIDC Revised Development Control Regulations 2009, as published by MIDC, deal with matters such as the occupancy certificate (regulation 12), clearances from other authorities including the Maharashtra Pollution Control Board (regulation 14), loading and unloading spaces (regulation 37) and fire protection and life safety (Part III, regulation 40). Newer regulations may apply to some MIDC areas, so confirm with MIDC which version applies to the specific plot.
06Commercial terms
- Rent and area basis: whether rent is on built-up, carpet or plot area, and how the area was measured. Measure it yourself.
- Lock-in: the lock-in period, and what happens if you need to exit early.
- Escalation: the escalation rate and how often it applies.
- Security deposit: amount, interest (if any), and the conditions and timeline for refund.
- Rent-free fit-out period: how long, and what happens if approvals or power enhancement take longer.
- Maintenance and outgoings: who pays for structural repairs, roof, common services, property tax, MIDC charges and insurance.
- Owner's works: a written list of what the owner will complete before handover (docks, levellers, power, flooring repairs) with dates.
- Exit: reinstatement obligations, and who owns the fit-outs you install.
- Stamp duty and registration: who bears the cost, and whether the agreement will be registered. Take your advocate's advice.
07Printable site-visit checklist
| Check | Why it matters | What to ask for / measure |
|---|---|---|
| Clear height | Decides racking levels and storage capacity | Measure to the lowest obstruction at eaves and centre; compare with racking plan |
| Floor load | Overloading damages the floor and racks | Written design load from the structural engineer; point and wheel loads |
| Floor condition | Cracks and uneven joints slow handling equipment | Inspect joints, cracks, levels; ask about surface type |
| Column grid | Poor grid wastes storage positions | Measure spacing both ways; overlay aisle plan |
| Docks and levellers | Dock count limits throughput at peak | Count, dock height, levellers, scope for more docks |
| Yard and turning | Trucks must manoeuvre safely off the road | Walk the largest vehicle's route; waiting space; surfacing |
| Access road | Approach can block heavy vehicles | Width, condition, restrictions; right-of-way document if private |
| Power | Shortfall stops machines or delays start-up | Sanctioned load and contract demand on the bill; transformer ownership and rating; enhancement route and cost |
| Water | Process and staff need assured supply | Source, sanctioned quantity, storage, recent bills |
| Drainage | Waterlogging damages goods and docks | Storm water route; monsoon history; effluent arrangement |
| Fire-fighting | Your use and storage must be covered | Installed systems; service records; fire NOC and what it covers |
| Crane readiness | Retrofitting a crane is costly | Structural drawing showing crane design and capacity |
| Roof and ventilation | Leaks and heat affect goods and people | Roof age, leaks, insulation, ventilators |
| Office and amenities | Shift operations need facilities | Toilets, canteen, security, separate staff entry |
| Title | The signer must have the right to lease or sell | Title documents; authority lease deed for leasehold plots |
| Building permission and OC | Unapproved structures carry risk | Approved plans, occupancy certificate, match with what is built |
| MPCB consent | Some activities need consent to operate | Existing consent and its activity; whether you need your own |
| MIDC permission | Ask whether a transfer or sub-lease needs MIDC's approval | Permission status, cost, applicable regulations for the plot |
| Dues and encumbrances | Arrears and claims can follow the property | Recent bills and receipts; encumbrance and litigation check |
| Commercial terms | Total cost is more than the headline rent | Lock-in, escalation, deposit, fit-out period, outgoings, exit |
08After the visit
Put every answer into the term sheet or agreement, with supporting documents attached. Treat anything said but not shown as unconfirmed until it is in writing and checked by your consultants.