01What this guide covers
An MIDC plot is not freehold. It is held on lease from the Maharashtra Industrial Development Corporation, so a sale of the plot, shed or gala (भूखंड / शेड / गाळा) is a transfer (हस्तांतरण) that MIDC must approve. MIDC also levies a charge when it does so.
This guide answers three questions from MIDC's own documents:
- 1Who in MIDC approves the transfer?
- 2What does MIDC charge, and on what basis?
- 3What documents and conditions should you expect?
Most of the sources are Marathi circulars. We give the key Marathi terms once so you can match them to the originals, which prevail. MIDC publishes its circulars on its circulars page.
02The documents behind this guide
| Document | Date | What it does | Status |
|---|---|---|---|
| Circular P121764 | 22.11.2023 | Sets the FSI-based differential charge on transfer | In force, amended by the corrigendum below |
| Corrigendum पी३९०८५३ | 08.04.2025 | Rewrites clause (1) of P121764 | Applied in this guide |
| Circular I/146338/2025 | 15.12.2025 | Revises who approves transfers of units in production | Latest document we hold |
| Citizen's Charter C12641 | 15.07.2013 | Lists services, documents, time limits and officers | Old; see below |
| Guidelines on Land Allotment System of MIDC | No date printed | Sets conditions for expansion allotments | Undated; see below |
03Who approves the transfer
What the December 2025 circular says
Circular I/146338/2025, dated 15.12.2025 and signed by MIDC's Chief Executive Officer, is titled "revision of the powers for transfer of industrial plots" (औद्योगिक भूखंडांचे हस्तांतरण अधिकारांमध्ये सुधारणा). It amends an earlier circular, P209217 dated 04.07.2025, which we have not seen.
It covers one category: transfer of industrial plots that have obtained a building completion certificate and are in production (इमारत पुर्णत्वाचा दाखला प्राप्त करून उत्पादन चालू असणाऱ्या औद्योगिक भूखंडांचे हस्तांतरण). For that category, the approving authority is:
| Plot area | Approving officer |
|---|---|
| Up to 20,000 sq m (चौ.मी.) | Regional Officer (प्रादेशिक अधिकारी) |
| Above 20,000 sq m | Deputy Chief Executive Officer (उप मुख्य कार्यकारी अधिकारी) |
The circular says nothing else in P209217 has changed, and it directs action "with immediate effect" (तात्काळ प्रभावाने).
What it does not cover: plots without a completion certificate, plots not in production, sheds, galas, and commercial or residential plots. For those, the authority comes from P209217 or other circulars we do not hold.
What the 2013 Citizen's Charter said
MIDC's English Citizen's Charter (No. MIDC/Joint C.E.O./Citizen's Charter/C12641/2013, dated 15/07/2013) set out the transfer slabs under Service 11, "Transfer of plot/shed/shop". For industrial plots:
- up to 15,000 sq m: Regional Officer;
- 15,001 to 30,000 sq m: Regional Officer, with approval of the Deputy Chief Executive Officer;
- 30,001 sq m and above: Regional Officer, with approval of the Joint Chief Executive Officer;
- plots allotted on priority basis, of any area: Regional Officer, with approval of the Joint Chief Executive Officer;
- plots, built-up shops and similar units in IT/BT parks: Regional Officer, with approval of the Joint Chief Executive Officer (IT).
The charter also gave separate slabs for built-up sheds and shops (1,000 and 2,000 sq m breakpoints), residential plots (100 and 500 sq m) and commercial plots and shops (500 and 2,000 sq m).
Where the two differ: for a completed industrial unit in production, the 2025 circular draws a single line at 20,000 sq m. The charter's 15,000 and 30,000 sq m slabs have been overtaken for that category. MIDC's revised Marathi Citizen's Charter of January 2018 also states that the 2013 charter is to be treated as cancelled. Use the 2013 charter only as background.
Practical tip: before you file, ask the Regional Office which circular it is applying to your case, and which officer will sign. This matters most for a plot that is not yet in production or has no completion certificate.
04What MIDC charges: the FSI-based differential
Background in the circular
Circular P121764 (क्रमांक: मऔविम/भूविभाग/मव्य(भूमी)/P121764, dated 22/11/23) explains that MIDC already transferred plots by charging a "difference amount" in rates based on construction (बांधकामावर आधारीत दरातील फरकाची रक्कम).
MIDC circulars of 21.06.2019, 02.08.2021 and 12.05.2023 then made it compulsory to build at least 40% of the permissible FSI (अनुज्ञेय चटई निर्देशांक). The transfer charge therefore had to be revised to match.
The Board considered the proposal at its 397th meeting on 17.10.2023 and passed resolution no. 6617. The circular was issued with the approval of the Chief Executive Officer.
The charge is expressed as a percentage "differential amount of the premium" (अधिमुल्यातील ... फरकाची रक्कम). P121764 does not itself state the amount the percentage is applied to. That base comes from MIDC's earlier transfer guidelines, which the circular lists as references and which we do not hold.
Clause (1): plots allotted before 21.06.2019 (as amended in April 2025)
This clause applies to plots and sheds that:
- were allotted by MIDC before 21.06.2019; and
- are in production while using less than 40% of the permissible FSI; and
- are the subject of an informal transfer (अनौपचारिक हस्तांतर). The circular does not define this term.
As amended by the corrigendum of 08.04.2025, the rule for these plots is:
| Construction done | Charge |
|---|---|
| 20% or more of permissible FSI (Basic) | 10% differential amount of the premium |
| Less than 20% of permissible FSI (Basic) | 30% differential amount of the premium |
What the corrigendum changed. The 2023 text measured the 20% "within the category-wise original development period" (प्रवर्गनिहाय मुळ विकास कालावधीमध्ये).
The corrigendum records that MIDC was then reading this as the initial development period in the primary agreement, counted from allotment. MIDC found this "not reasonable" (संयुक्तिक नसल्याने), so it deleted the time-period words from clause (1). The test now looks only at whether 20% of Basic FSI has been built.
The corrigendum states that nothing else in P121764 has changed.
Clause (2): plots allotted after 21.06.2019
This clause applies to plots and sheds allotted after 21.06.2019 whose agreement has been executed, again in cases of informal transfer. It refers to the circular of 12.05.2023, under which a category-wise "blanket extended development period" (सरसकट वाढीव विकास कालावधी) applies.
| Construction done within that extended development period | Charge |
|---|---|
| 40% or more of permissible FSI (Basic) | 10% differential amount of the premium |
| Less than 40% of permissible FSI (Basic) | 30% differential amount of the premium |
The circular adds a worked example (उदा.) for "A" category ("अ" प्रवर्ग) industrial areas. It covers plots allotted on priority, by online direct allotment or by e-bidding, and plots given a two-year development period after transfer:
- During the original development period. The holder must build 20%. A holder who has built 20% or more and then applies to transfer pays the 10% differential. Otherwise the charge is 30%.
- After the original development period ends. The 12.05.2023 circular gives two more years to build the remaining 20%. A holder who has built 40% or more in total within that period and then applies to transfer pays the 10% differential. Otherwise the charge is 30%.
Illustration of the printed formula
Using symbols only:
- B = built-up construction, as a share of permissible Basic FSI;
- D = the differential premium amount, as defined in MIDC's transfer policy;
- T = the construction threshold: 20% under clause (1) as amended, or 40% under clause (2).
The circular's rule is: if B ≥ T, the charge is 10% of D; if B < T, it is 30% of D.
We do not put rupee figures on D, because the held circular does not define it.
Practical tips on the charge
- Before you agree a price, ask the seller for the allotment date, the sanctioned plans and the completion certificate. The allotment date (before or after 21.06.2019), the FSI actually built and the development-period position decide whether the 10% or the 30% band applies.
- Ask the Regional Office for a written demand of the differential amount before you commit, and agree in the sale terms who pays it.
- Clause (1) covers only pre-2019 plots that are in production using less than 40% of FSI. The circular does not say how pre-2019 plots using 40% or more are charged. Ask MIDC.
05Documents and time limits (2013 charter)
What the charter listed
Service 11 of the 2013 charter listed these documents for a transfer of a plot, shed or shop:
- 1The original plot holder's request or online application, with a resolution if the holder is a company or institution.
- 2The transferee's request application, with a resolution if a company or institution.
- 3The prescribed application form, filled by the transferee.
- 4The transferee's Detailed Project Report (DPR).
- 5An NOC and no-encroachment certificate from MIDC's Executive Engineer, Deputy Engineer or SPA.
- 6An NOC from the Labour Commissioner, if applicable.
- 7Evidence of the relationship, for a transfer to a blood relation.
- 8For an heirs' claim: the heir's application, the death certificate, and an heirship certificate from a competent court or a declaration in the prescribed format.
- 9A notarised undertaking from the transferee. It covers water use, pollution control, built-up construction, employment and the estimated time to start production.
- 10The prescribed processing-fee cheque. No amount is given in the charter.
The service time was 15 days after submission of a complete ("perfect") application.
Service 12, sub-division of a plot and transfer of the sub-divided plot, had a similar list plus a sub-division map report from MIDC's engineer and a no-dues certificate. Its time limit was 21 days, with approval by the Minor Modification Committee.
Practical tip: this list is from 2013, and that charter has since been cancelled, so treat it as a starting checklist only. Ask the Regional Office for the current list and the current processing fee, and check whether the application now goes through MIDC's online system.
06When a transfer is not allowed: expansion plots
What the guidelines say
MIDC's "Guidelines on Land Allotment System of MIDC" carries no date or reference number. Under "Land Allocation for Expansion Purpose", item 6 (p. 8) states:
"No permission will be given for transfer of plot for next 5 years and for sub-letting of plot."
The guidelines do not say from which date the 5 years run.
MIDC's current allotment policy is MILAAP 1.0 of 17.10.2025 (see How MIDC plots are allotted). We found no plot-transfer rule in it. Its use of "transfer" refers to moving applications between Land Allotment Committee meetings.
Practical tip: if the plot or any part of it came to the seller as an expansion allotment, check the allotment letter and lease for a no-transfer period before going further.
07Gaps you should know about
We have not seen the following MIDC circulars, and any of them may change what is described above:
- P209217, dated 04.07.2025, the transfer-powers circular that the December 2025 circular amends;
- P221365, dated 06.08.2025;
- P208241, dated 13.05.2026, on transfer and sub-lease of plots allotted under section 15(b);
- A97720, dated 21.03.2022, on refunds;
- the earlier transfer guidelines and circulars that P121764 lists as references, which define the premium base.
Check the MIDC circulars page for anything issued after 15.12.2025.
08Summary
- A transfer of an MIDC plot, shed or gala needs MIDC's approval.
- For a completed industrial unit in production, the Regional Officer approves up to 20,000 sq m and the Deputy CEO above that (15.12.2025).
- MIDC levies a differential charge of 10% or 30% of the premium, depending on whether the plot crosses the FSI construction threshold: 20% for pre-21.06.2019 plots in production after the April 2025 corrigendum, and 40% for later plots.
- Expansion allotments carried a five-year bar on transfer under MIDC's undated guidelines.
- Confirm the current position with the Regional Office before you sign.