If you need a shed in an MIDC industrial area, there are two common routes. You can take space from an existing plot holder on a leave-and-licence or rental arrangement, or you can buy the plot or shed from that plot holder. Each route runs through an MIDC permission. Taking space is sub-letting (पोटभाडे, potbhade) and needs MIDC's sub-letting permission. Buying is a transfer and needs MIDC's transfer approval.

This guide sets out what MIDC's documents say about both permissions and the questions to ask before choosing. It does not compare market rents or prices, and it does not tell you which route is better for your business.

01The documents behind this guide

The main source is MIDC's sub-letting circular No. क्र.मऔविम/भू-विभाग/म.व्य.(भूमी)/ P२७१३०२ dated 20/04/2026, which revises the sub-letting rates for plots and built-up areas. The guide also draws on MIDC's 2013 Citizen's Charter (No.MIDC/Joint C.E.O./Citizen's Charter/C12641/2013), the undated Guidelines on Land Allotment System of MIDC, and three transfer circulars: P121764 dated 22/11/2023, its corrigendum पी३९०८५३ dated 08.04.2025, and I/146338/2025 dated 15.12.2025. The circulars are in Marathi; MIDC lists them on its circulars page.

02Route 1: taking space from a plot holder (sub-letting)

What the circular says

The April 2026 circular begins by explaining why MIDC revised the rates (p. 1):

  • MIDC had made sub-letting an online service with automation and self-certification. A successful online application produces the permission order immediately as an auto-generated order. By the circular's date, only 360 applicants had used the automated service.
  • MIDC continued to find cases where space was sub-let without permission.
  • When a plot holder gives space in a building on its plot on sub-let, MIDC levies a sub-letting charge on the area actually let. The charge is worked out at that year's prevailing rate, according to industrial or commercial use.
  • Because the charge was high, many plot holders let space without MIDC's prior permission. Some were also not using the plot as MIDC's policy permits. In those cases MIDC levies the sub-letting charge and a penal charge, and interest on top of both. Plot holders were not paying these large amounts, so the cases stayed pending.
  • MIDC ran "special schemes" on 17/11/2015 and 21/06/2021 to regularise sub-letting for industrial purposes that had been done without permission.

On p. 2 the circular records that industry associations had asked MIDC to reduce the rates. MIDC's Board considered a proposal at its 410th meeting on 24.03.2026 and passed resolution No. 7148. The revision has two stated aims. The first is to reduce the charge for plot holders who sub-let with MIDC's permission, so that more of them use the service. The second is to keep control over those who sub-let without permission.

The revised rates are printed as follows (p. 2, translated from Marathi):

CircularRate per sq. m. per yearPenal rate for area let without permission, per sq. m. per year
Circular dated 26.05.20101.5 per cent of the prevailing rate18 per cent of the prevailing rate
Circular dated 25/06/2019 for sub-letting of plots in Information Technology parks0.5 per cent of the prevailing rate, according to industrial or commercial use9 per cent of the prevailing rate, according to industrial or commercial use

The circular also says the following (p. 2):

  • The revised rates apply from the date of the circular.
  • Plot holders who have already been issued a demand (मागणीपत्र, Demand) for sub-letting charges continue to pay the rates that applied before this circular.
  • Apart from these changes, no other change has been made to the sub-letting circulars.

The circular does not define "prevailing rate" (प्रचलित दर), does not set the earlier rates beside the new ones, and does not say what happens to an occupier of space sub-let without permission. This guide therefore gives no worked rupee figures.

What the Citizen's Charter lists for a sub-letting permission

The 2013 Citizen's Charter (Service 10, p. 10) lists these documents for "Subletting of plot":

  1. 1Request application from the plot holder.
  2. 2Request application of the tenant.
  3. 3Block plan of the area for subletting.
  4. 4Detail Project Report of the sublease.
  5. 5"Live and license agreement with registration certificate" (as printed).
  6. 6Sub-tenant resolution (partnership deed / Memorandum & Articles of Association).
  7. 7Approval letter, if the plot is kept as security with a bank for a loan.

The Charter gives 7 days from submission of a complete application as the period for the service, and names the Regional Officer as the officer providing it. The Charter is dated 2013. The 2026 circular describes an online process with an auto-generated order, so check MIDC's current online requirements before relying on this list.

Expansion plots: no sub-letting permission

The undated land-allotment guidelines cover land allotted for expansion purposes (section 4, pp. 7–8). Item 6 reads: "No permission will be given for transfer of plot for next 5 years and for sub-letting of plot." The sentence does not make clear whether the five-year period also applies to sub-letting, or whether sub-letting is barred altogether. Treat an expansion plot as a red flag until MIDC confirms the position in writing.

Practical tips if you are taking space

  • Ask the plot holder whether MIDC sub-letting permission exists, or will be obtained, for your area. If it exists, ask for a copy of the order. The circular shows that MIDC knows about unpermitted sub-letting and charges penal rates and interest on it.
  • Agree in writing who bears the sub-letting charge. The circular describes MIDC levying the charge on the plot holder. Whether any of it is passed on to you depends on your agreement, so settle it before you sign.
  • Match the permission to your actual use. The charge depends on industrial or commercial use and on the area actually let, so the permission should describe your real use and area.
  • Register the leave-and-licence agreement. The Charter lists a registration certificate among the documents.
  • Ask whether the plot is mortgaged. If it is, the Charter lists the bank's approval letter among the documents.
  • Ask whether the plot was an expansion allotment (see above).
  • Ask whether a sub-letting demand is already pending. If MIDC issued a demand before 20/04/2026, the circular says the earlier rates continue to apply to it.
  • Check the building on site as well as the papers. Our site-visit checklist covers the physical and approval checks.

03Route 2: buying the plot or shed (transfer)

When you buy an MIDC plot or shed from its current holder, MIDC treats the deal as a transfer of the plot, shed or gala, and MIDC must approve it. This section summarises the points that matter for the lease-or-buy decision. A separate guide covers transferring an MIDC plot in detail.

What the circulars say

FSI-based differential amount (22/11/2023, corrected 08.04.2025). When a plot, shed or gala is transferred, MIDC charges a differential amount. The amount is a percentage of the premium (अधिमूल्य, adhimulya), and the percentage depends on how much of the permissible basic FSI has been built:

  • Plots allotted before 21.06.2019 and in production using less than 40 per cent of the permissible FSI (item 1, as corrected in 2025):
    • if construction is 20 per cent or more of the permissible FSI (Basic), the differential amount is 10 per cent of the premium;
    • if construction is below 20 per cent, it is 30 per cent.
  • Plots allotted, with the agreement executed, after 21.06.2019 (item 2, p. 2): the test is whether 40 per cent or more of the permissible FSI (Basic) has been built within the extended development period under the 12.05.2023 circular:
    • if it has, the differential amount is 10 per cent of the premium;
    • if not, it is 30 per cent.
    • The circular's worked illustration is in words only: 20 per cent construction within the original development period, then 40 per cent in total within the next two years.

The 2025 corrigendum removed the words "within the category-wise original development period" from item 1 (p. 1). It made no other change.

Who approves (15.12.2025). Some industrial plots have a building completion certificate and are in production. For their transfer, the approving authority is:

  • the Regional Officer, for areas up to 20,000 sq. m.;
  • the Deputy Chief Executive Officer, for areas above 20,000 sq. m.

This circular amends an earlier circular dated 04.07.2025, which is not held for this guide. The 2013 Charter (Service 11, pp. 10–11) has older area slabs for plots and separate slabs for built-up sheds. The Charter's slabs for built-up sheds are:

  • up to 1,000 sq. m.: Regional Officer;
  • 1,001–2,000 sq. m.: Regional Officer, with approval of the Deputy Chief Executive Officer;
  • 2,001 sq. m. and above: Regional Officer, with approval of the Joint Chief Executive Officer.

The Charter also lists a 15-day service period and documents that include the buyer's application and Detailed Project Report, an NOC and no-encroachment certificate from MIDC's Executive Engineer / Deputy Engineer / SPA, a Labour Commissioner NOC where applicable, a notarised undertaking and a processing fee. It contains no transfer fee figures.

Practical tips if you are buying

  • Ask how much of the permissible FSI has been built, and when the plot was allotted. These two facts decide which percentage of the premium applies under the 2023 circular. Get the figures from the approved plans and completion documents, not from a verbal estimate.
  • Ask whether the building completion certificate has been obtained and the unit is in production. The December 2025 approval slabs are written for that category of plot.
  • Ask whether the plot was an expansion allotment. The guidelines bar transfer permission for five years on expansion allotments.
  • Ask MIDC for the premium and the resulting amount for the specific plot. The circulars give percentages but not the figure for your plot.

04Leasing or buying: questions to settle first

The circulars do not tell you which route is better. They do show where each route depends on MIDC, and what to settle before you commit.

QuestionIf you take space (sub-letting)If you buy (transfer)
Whose MIDC permission is needed?The plot holder applies for sub-letting permission, with your application as tenant (Charter, Service 10).MIDC's transfer approval, applied for by the current holder together with you as transferee (Charter, Service 11).
What MIDC charge is described?A yearly sub-letting charge per sq. m. on the area let, at a percentage of the prevailing rate; penal rates for area let without permission (2026 circular).A one-time FSI-based differential amount as a percentage of the premium, depending on construction (2023 circular, 2025 corrigendum).
Who approves?Regional Officer (2013 Charter); online auto-generated order (2026 circular).Regional Officer or Deputy Chief Executive Officer, by area, for plots with a completion certificate and in production (15.12.2025 circular).
What stops it?Expansion allotments: no sub-letting permission (undated guidelines).Expansion allotments: no transfer permission for five years (undated guidelines).
What to ask the ownerExisting permission order, use and area permitted, pending demand, mortgage and bank approval.Allotment date, FSI built, completion certificate, production status, MIDC dues.

Beyond MIDC's charges, how long you need the space, whether your process needs building changes and how much capital you want to commit are commercial judgements for your own team and advisers; nothing in these circulars decides them.

05Points still to be confirmed

The April 2026 circular does not define "prevailing rate", and the 2009, 2010 and 2019 sub-letting circulars it amends, and the July 2025 transfer circular, are not held for this guide. Confirm these, and MIDC's current online document list, with the Regional Office before you sign.