A project's MahaRERA registration runs until the completion date the promoter declared. What happens when that date passes, and how a promoter can get more time, is set partly by the RERA Act and the Maharashtra Rules, and partly by MahaRERA's own orders. Our guide to registration validity, extension and lapse covers the Act and the Rules. This guide covers three MahaRERA orders on the same subject.
Throughout, "the order says" means the text of that order says so. "Practical tip" means a suggestion of ours that goes beyond the words of the order. No decided cases are covered. The guide is equally relevant if you are buying a new office or shop in a registered project.
01The three orders at a glance
| Order | Date | What it requires (as printed) | Who it affects | Pinpoint |
|---|---|---|---|---|
| Order No. 24/2021, "Procedure for validation of Form-4 (Architect's Certificate on Completion of Project)" | 21/09/2021 (handwritten) | Sets out what a promoter of an expired project must do, depending on whether Form 4 and the OC are uploaded and whether there is "sold inventory"; if the promoter "does not apply for extension, or does not respond", the "Allottee's society can apply to Authority under section 7" | Promoters of expired projects; allottees' societies | Parts A and B |
| Order No. 40/2022, "Extension of validity of the project registration under Section 7 (3)" | 27/12/2022 (handwritten) | A promoter who cannot get the required 51% consent "shall submit the consents as obtained from the allottees irrespective of the number of such consents", with reasons, an explanatory note and the steps to complete the project | Promoters seeking extension under section 7(3); allottees | Directions (a)-(h) |
| Order No. 66/2026, "Extension of registration of real estate projects due to Force Majeure under Section 6" | 07.08.2026 | Projects whose completion dates "fall on or after 28.02.2026, shall stand extended by four months", "automatically, without requiring submission of any separate application" | Promoters and buyers in registered projects with those dates | Paras 1-3 |
02Order No. 24/2021: projects whose registration has expired
The order says that at the time MahaRERA had registered 30668 projects, of which 7214 were completed, and that "3371 projects have expired and Promoters have not applied for extension of the project date nor uploaded the Form 4". It records that "A list of expired projects has now been uploaded, on our portal."
The order then sorts expired projects by what the promoter has uploaded. Form 4 is the "Architect's Certificate on Completion of Project"; OC is the occupancy certificate.
Part A: Form 4 with an OC
- Form 4 with the OC "within the date of completion": "Can be validated as correct."
- Form 4 with the OC "received after date of completion":
- "If there is no sold inventory, promoter can apply in correction module and completion date can be corrected."
- If there is sold inventory, the "Promoter has to apply for extension which will be valid up to the date of OC. (As project has been completed, post facto extension may be granted.)"
Part B: Form 4 but no OC or part OC, or no Form 4 or OC at all
In both situations, if there is no sold inventory, the promoter "can apply in correction module and completion date can be corrected". If there is sold inventory, the order gives three routes, joined by "OR":
- 1"apply for extension under section 6 if applicable";
- 2apply "for extension under section 7(3) with at least 51% allottees consent";
- 3"If consents are less than 51%, apply with available consents", in which case the "Authority may set up a joint Hearing with allottees and may consider extension with additional conditions" (for a project with no Form 4 or OC, the words are "may set up Hearing with allottees").
For a project that "is expired but no Form 4 or OC is uploaded", the order adds a further step (item (v)) that matters to buyers: "If promoter does not apply for extension, or does not respond, then Allottee's society can apply to Authority under section 7, and after Hearing, appropriate order will be passed by the Authority."
Practical tip: If your project's completion date has passed and the MahaRERA page shows neither an extension nor Form 4, ask the promoter in writing which of these routes it is following.
03Order No. 40/2022: extension under section 7(3) without 51% consent
Section 7(3) of the Act lets MahaRERA, instead of revoking a registration, "permit it to remain in force subject to such further terms and conditions as it thinks fit to impose in the interest of the allottees". Order No. 40/2022 deals with extensions sought under that provision.
The order says MahaRERA's earlier Order No. 7 of 2019 dated 08.02.2019 had resolved that, where a promoter "is unable to complete the project in the extended time of one year, granted under Section 6, further extension may be given only in those cases where the concerned association of allottees resolve" that the existing promoter be permitted to complete the project "in a specific time period". It then records that allottees were not giving consent, for reasons including that "If consent is granted, the complaint filed before the Authority would be dismissed" and that they "Do not have confidence that the promoter shall complete the project".
MahaRERA's stated concern was that withheld consent "results in lapsing of the registration of the real estate project which is not in the interest of the allottees as the said real estate project then cannot be executed and completed by the promoter for want of project registration."
The directions are:
- 1Extension "would be granted, on promoters complying with the directions issued under Order No. 7 of 2019 dated 08.02.2019" (direction (a)).
- 2If promoters cannot comply with (a), they "shall submit the consents as obtained from the allottees irrespective of the number of such consents along with reasons why the required percentage of consents from allottees could not be obtained and why the application for extension should be considered without the required 51% consent" (direction (b)(i)).
- 3They must also submit an explanatory note on the "grounds and reasons for delay" and the "need for grant of extension", with supporting documents, and "shall also state the steps that would be taken by him to complete the project within the extended period sought" (direction (b)(ii)).
- 4The application is made in Form 'E' under rule 7(1), with fees calculated under rule 7(3) (directions (c) and (d)).
- 5"Consents of allottees shall be provided in Format 'B' as provided in Circular No. 28 of 2021 dated 08.03.2021" (direction (e)).
- 6"Promoters shall be bound by the further terms and conditions as may be imposed by the Authority in the interest of the allottees" (direction (f)).
- 7The order is to "be read along with Order No. 7 of 2019 dated 08.02.2019" (direction (h)).
For buyers, direction (g) is the key line:
"The grant of extension of the project validity shall not affect /jeopardize the rights accrued in favour of the allottees who have booked their plot, or unit or apartment or building in the said real estate project"
Practical tip: If a promoter asks you to sign a consent for extension, ask for the Format 'B' document and read it before signing. Direction (g) says an extension does not affect your accrued rights; it does not say what a particular consent form contains.
04Order No. 66/2026: the automatic four-month extension
The order says the Ministry of Finance, by Office Memorandum dated 29.04.2026, "has treated the prevailing West Asia situation as 'War' for the purpose of invocation of the Force Majeure", and that the Ministry of Housing and Urban Affairs, by Advisory No. O-17024/66/2018-HOUSING-UD/E-9042100 dated 31.07.2026, advised regulators to extend registrations "by four months" instead of requiring separate applications. "War" is one of the events named in the definition of force majeure in section 6 of the Act.
Acting under sections 6 and 37 of the Act, MahaRERA ordered:
- 1"The registered projects whose completion dates, revised completion dates or extended completion dates fall on or after 28.02.2026, shall stand extended by four months. However, projects registered on or after 01.08.2026, shall be excluded from this extension."
- 2"The aforesaid extension shall be granted automatically, without requiring submission of any separate application by the promoter."
- 3"The Registration and IT cell, MahaRERA, shall make necessary changes in the records and on the MahaRERA web portal to give effect to this Order."
The order came "into force with immediate effect".
Practical tip: The order extends the registration's completion date. It does not say anything about the possession date in your agreement for sale. If a promoter cites this order, compare the date on the MahaRERA project page with your agreement, and ask in writing how the promoter says it affects your possession date.
05What a buyer should check if a project is lapsed or extended
- 1Find the completion date on the project page and note whether it is the original, revised or extended date (Order 66/2026, para 1).
- 2Check whether Order 66/2026 applies: was the completion date on or after 28.02.2026, and was the project registered before 01.08.2026? (Order 66/2026, para 1).
- If it applies, check that the portal shows the four-month extension (para 3).
- 3If the date has passed with no extension, check whether Form 4 and the OC are uploaded (Order 24/2021, Parts A and B).
- 4Find out which route the promoter is using: correction module, section 6 or section 7(3) (Order 24/2021, Part B).
- 5If consent is being sought, ask for the Format 'B' consent and the promoter's stated steps to complete (Order 40/2022, directions (b)(ii) and (e)).
- Remember that an extension "shall not affect /jeopardize" accrued allottee rights (direction (g)).
- 6Ask whether the allottees' society has applied under section 7 if the promoter has not applied or responded (Order 24/2021, Part B, item 2(v)).
- 7Keep dated copies of the project page and the promoter's replies.
Our guide to checking a project on MahaRERA explains how to read the project page. If you need to take a matter to MahaRERA, see how a MahaRERA complaint works.
06What this guide does not cover
This guide does not cover Order No. 7 of 2019 or Circular No. 28 of 2021 (both referred to in Order No. 40/2022 but not reviewed), other MahaRERA orders or circulars, how MahaRERA has decided individual extension applications, or case law. Whether Order No. 40/2022 changes any part of Order No. 24/2021 is not stated in either order. It is information only and not legal advice.