Setting up a factory on land of the Maharashtra Industrial Development Corporation (MIDC) is a chain of separate permissions, each under its own document. This page puts the chain in order and links to the guide that covers each step.

"The document says" means the text of an official MIDC or Government of Maharashtra document. "Ask" marks a point the documents leave open, which you should confirm in writing before you rely on it.

01Start here: which route to land?

There are three ways to get MIDC industrial space, and the rest of the sequence depends on which you take:

  • A fresh allotment of a vacant plot from MIDC.
  • Buying an existing plot or shed from its current holder. MIDC treats this as a transfer.
  • Taking space in an existing building on someone else's plot. MIDC treats this as sub-letting.

The document says: MIDC's Pricing Policy circular of 16 October 2025 states that applications are accepted only through MIDC's online portal, and that all vacant plots in MIDC's industrial areas are to be shown on it continuously. Whether a fresh plot is even available in your target area is therefore the first thing to check.

02The master sequence

  1. 1Decide the route to land, then check what is actually available.
    • Fresh allotment: look for a vacant plot on MIDC's listings first.
    • If none is listed, the routes are a transfer or permitted sub-letting (steps 3 and 4).
  2. 2If you want a fresh plot, apply under MILAAP 1.0 and understand the rate band.
  3. 3If you are buying an existing plot or shed, plan for MIDC's transfer approval and differential charge.
  4. 4If you are taking space in a building, or deciding between leasing and buying, check sub-letting permission.
  5. 5Inspect the building or site physically.
  6. 6Get building permission before any construction.
  7. 7Fire NOC, completion and occupancy.
    • Provisional fire NOC with the building plan; plinth intimation; then completion, final fire NOC and occupancy.
  8. 8Work out which incentive policy, if any, applies to your dates and taluka.
  9. 9Check the specific industrial area.
    • For two of the industrial areas around Pune: the Chakan MIDC guide and the Talegaon MIDC guide.
    • Steps 8 and 9 are questions to settle before you sign at steps 2 to 4, even though they appear here at the end of the paperwork.

03Step by step: what the documents say

Steps 1 and 2: a fresh plot under MILAAP

The document says: MIDC's circular of 17 October 2025, MIDC Industrial Land Application and Allocation Policy (MILAAP 1.0), sets out three allotment routes, each with its own Land Allotment Committee (p. 4):

  • A. Direct allotment without bidding, by application, for important projects.
  • B. Allotment by cap e-bidding, for categories decided by the CEO.
  • C. Open e-bidding, for commercial and residential plots and galas, and industrial galas and sheds.

The circular also says:

  • every application must be made online on the MILAAP portal, and an application and processing fee of Rs 10,000 to Rs 50,000 plus GST applies, depending on the area demanded (p. 19);
  • on the bidding routes, the applicant deposits earnest money of 5% of the plot price at the upset rate online with the application (pp. 15 and 18; MSME reserved plots are excluded on route B);
  • rates under MILAAP follow MIDC's Pricing Policy (p. 19);
  • the development period, minimum use of floor space index (FSI) and extensions of time follow MIDC's prevailing policy, which the circular does not set out (p. 19);
  • plots surrendered, or taken back for not being developed in time, go straight back onto the vacant plot list (p. 20);
  • the policy applies from 3 September 2025 (p. 20).

The Pricing Policy of 16 October 2025 says the upset rate is the prevailing rate plus 10%, that a bid must fall within the band between the upset rate and the cap rate (p. 2), that a 9% increase applies from 1 April every year (p. 3), and that the cap is 50% above the upset rate in zones A and B and in metropolitan and municipal corporation areas, and 25% in zones C, D and D+ (p. 5).

Ask: which zone your target area falls in. The held circulars use zones A to D+ but do not list which industrial areas fall in which zone.

Step 3: buying an existing plot or shed

The document says: MIDC's circular P121764 of 22 November 2023 records that MIDC circulars of 21.06.2019, 02.08.2021 and 12.05.2023 made it compulsory to build at least 40% of the permissible FSI, and it revises the transfer charge to match (p. 1). On transfer, MIDC levies a differential amount of 10% or 30% of the premium, depending on whether a construction threshold of permissible basic FSI has been met (pp. 1–2, clause (1) as amended by the corrigendum of 8 April 2025, p. 1).

For a completed industrial unit in production, the circular of 15 December 2025 makes the Regional Officer the approving authority up to 20,000 sq m and the Deputy Chief Executive Officer above that (p. 1).

Unresolved: the circulars express the charge as a percentage "differential amount of the premium" but do not define the amount the percentage is applied to. That base sits in earlier transfer guidelines we do not hold. We do not explain it or estimate it; ask MIDC for a written demand for your plot.

Step 4: taking space by sub-letting

The document says: MIDC's circular of 20 April 2026 describes sub-letting as an online service with an auto-generated permission order (p. 1). It also says that where space is sub-let without permission, MIDC levies the sub-letting charge and a penal charge, with interest (p. 1). The charge is set as a percentage of a "prevailing rate" (p. 2), which the circular does not define.

MIDC's undated land-allotment guidelines say, for land allotted for expansion: "No permission will be given for transfer of plot for next 5 years and for sub-letting of plot" (p. 8). The sentence does not make clear whether the five years also apply to sub-letting.

Step 5: the site visit

For storage use on an MIDC plot, the 2023 regulations say industrial godowns are permissible "subject to approval of MIDC on the plots allotted by MIDC" (CDCPR Reg. 4.2.1(ii), Gazette p. 76). The Logistics Policy 2024 allows warehouse height up to 24 m "as per fire department norms and availability of road width" (English text, PDF pp. 51 and 55); that is a conditional ceiling, not a height every site gets.

Step 6: building permission

The document says: under MIDC's Comprehensive Development Control and Promotion Regulations (CDCPR), sanctioned by Urban Development Department notification dated 5 July 2023:

  • no person may erect, alter or demolish a building without first obtaining a building permit, development permission or commencement certificate from MIDC (Reg. 2.1.1, Gazette p. 39);
  • the application is accompanied, where applicable, by clearances from other departments, including the Maharashtra Pollution Control Board (Reg. 2.2.12, p. 47, as amended in 2025).

Step 7: fire, completion and occupancy

The document says:

  • A "special building" includes any building used for industrial or storage occupancy with a floor area of more than 500 sq m on any one or more floors (Reg. 1.3(111)(xiv), p. 30). The special-building rules below depend on this definition.
  • MIDC's provisional fire NOC is applied for online through MIDC's single-window system (BPAMS), in one combined application with the building plan, provisional fire NOC, temporary water connection and external drainage connection (provisional fire NOC procedure, p. 1). The procedure document carries no date.
  • The owner intimates MIDC when work reaches plinth level, in Appendix F, before construction continues (Reg. 2.8.3, p. 54).
  • For special buildings, the completion certificate is accompanied by the final fire NOC from MIDC's Chief Fire Officer (Reg. 2.9, p. 54).
  • MIDC issues or refuses the occupancy certificate within 21 days of receiving the completion certificate, failing which the work is deemed approved for occupation if it conforms to the sanctioned plans. For special buildings, the occupancy certificate follows the Chief Fire Officer's clearance (Reg. 2.10, pp. 54–55).

Ask: the current BPAMS checklist, and the procedure for the final fire NOC. Neither is set out in the documents behind our guides.

Step 8: incentives

The document says:

  • The Maharashtra Industries, Investment and Services Policy 2025 was approved by a Government Resolution dated 31 December 2025. The GR says incentives under the policy are to be paid under the Package Scheme of Incentives, that the existing 2019 scheme is to be amended, and that a new Package Scheme of Incentives is to be declared (GR p. 3, para 1(7)).
  • The Package Scheme of Incentives 2019 was to remain in operation from 1 April 2019 to 31 March 2024 "or till the new Package Scheme of Incentives comes into force" (p. 2).
  • For the Pune division, the 2025 policy's annexure states that the classification as on 1 April 2019 remains valid for the 2025 policy period. It lists Maval in Group A, and Khed in Group A within the Pune Metropolitan Region and Group C outside it (PDF p. 148). It classifies talukas, not MIDC areas.
  • The 2025 policy describes MAITRI as the State's single-window facilitation mechanism, with an online portal at maitri.maharashtra.gov.in (PDF p. 98).

Unresolved: how a project begun under the 2019 scheme is treated after the 2025 policy. The new Package Scheme of Incentives that the GR says will be declared is not among the documents we hold, and the GR contains no transition clause. Ask the District Industries Centre or the Development Commissioner (Industries) which scheme your dates fall under before relying on any incentive.

Step 9: the industrial area

The document says: MIDC's Land Bank, as captured on 15 November 2026, showed 0 plots available in each of Chakan Ph-1 to Ph-5, and 2 in Talegaon Ph-4 and 4 in Talegaon Ph-5, with 0 in the other Talegaon rows (Land Bank captures, p. 1). The Land Bank prints no effective date; re-check it on the day you plan.

04Step, authority and guide at a glance

StepAuthority / documentDetailed guide
Fresh plot allotmentMIDC; MILAAP 1.0 circular, 17 October 2025MILAAP allotment guide (step 2)
Plot priceMIDC; Pricing Policy circular, 16 October 2025Allotment rates guide (step 2)
Buying an existing plot or shedMIDC Regional Office or Deputy CEO; transfer circulars of 22 November 2023, 8 April 2025 and 15 December 2025Plot transfer guide (step 3)
Taking space in a buildingMIDC; sub-letting circular, 20 April 2026Lease-or-buy and sub-letting guide (step 4)
Physical and document checksYour consultants; no single authoritySite-visit checklist (step 5)
Storage or logistics useMIDC (CDCPR 2023); Industries Department (Logistics Policy 2024)Warehouse and logistics park guide (step 5)
Building permissionMIDC as planning authority; CDCPR 2023Factory building approvals guide (step 6)
FSI and setbacksMIDC; CDCPR 2023Planned FSI and setbacks guide (step 6)
Fire NOC, completion, occupancyMIDC and its Chief Fire Officer; CDCPR 2023; provisional fire NOC procedureFactory building approvals guide (step 7)
IncentivesIndustries Department, Development Commissioner (Industries), District Industries Centre; 2025 policy GR, PSI 2019Incentive policy guide (step 8)
Industrial areaMIDC Land Bank and Land Rates pagesChakan and Talegaon guides (step 9)

05Decisions only you can make

The documents set conditions; they do not choose for you. Before you commit, settle these within your own team and with your advisers:

  • New plot, transfer or sub-letting. Which route fits your timeline, capital and risk appetite.
  • Location. Which industrial area and taluka, weighed against your workforce, suppliers and customers.
  • Size. How much land or built space you need now, and whether you are planning for expansion.
  • Building programme. What you will build, and whether you can meet MIDC's construction and development-period conditions for the plot.
  • Process and storage. Your raw materials, finished goods and quantities; the fire NOC and other clearances depend on them.
  • Capital and phasing. Your fixed capital investment and employment plan, which feed any incentive class.
  • Dependence on incentives. Whether the project still works if no incentive is available on your dates.
  • Who pays MIDC's charges. In a transfer or sub-letting deal, which party bears the differential amount or sub-letting charge.
  • Your advisers. The architect, structural engineer, fire consultant, advocate and tax adviser who will check each step for your plot.
  • What to get in writing. The zone and cap for your area, the development period, the transfer premium base or sub-letting rate, and the incentive scheme for your dates: the open points flagged "Ask" and "Unresolved" above.