A fire no-objection certificate (NOC) decides two moments in an industrial project on MIDC land: whether your building permission is issued, and whether you can occupy the building once it is built. This guide explains, from MIDC's own documents, which buildings need fire clearance, who grants it, and what the regulations expect at the provisional and final stages.
For the full sequence of approvals, from building permission to occupancy certificate, see building a factory on an MIDC plot. This guide goes deeper on the fire side only.
Throughout, "the regulation says" means the text of the source says so. "Practical tip" means a suggestion of ours that goes beyond the words of the source.
01The sources, and how current they are
- CDCPR 2023. The Comprehensive Development Control and Promotion Regulations for MIDC, sanctioned by Urban Development Department notification No. TPB-4322/314/CR-25/2022/UD-11 dated 5 July 2023, in force from Gazette publication on 13 July 2023. Chapter 9 is headed "Fire Protection & Life Safety". Page numbers below are Gazette page numbers.
- The 2025 corrigendum (No. TPB-4324/1079/C.R.15/2025/UD-11, dated 21 May 2025). Where it changes a provision cited here, this guide says so.
- MIDC's provisional fire NOC procedure. A 12-page MIDC document headed "Provisional Fire NOC". It carries no date, and it refers to NBC-2005, while the CDCPR refers to the National Building Code of India, 2016. Treat it as an indication of MIDC's process, not a current fee schedule.
02Which buildings need MIDC's fire clearance?
The regulation says (Reg. 9.0, p. 144): Chapter 9 applies "to special buildings as mentioned in Regulation no. 1.3(111)(xiv)". A note adds that an owner may choose to apply it to other buildings too.
A "special building" (Reg. 1.3(111)(xiv), p. 30) includes any building 24 m or more in height, any hazardous building more than 15 m high, and any building used for industrial, storage or hazardous occupancy (among others) "where any of these buildings have floor area more than 500 sqm on any one or more floors". Basements also bring a building in: two or more basements, or one of more than 500 sqm.
For special buildings, the regulations require:
- a fire clearance of the building scheme before the building permission is sanctioned (Regs. 2.2.12, p. 47, and 2.6.1(ii), p. 51);
- the final fire NOC with the completion certificate (Reg. 2.9, p. 54);
- the Chief Fire Officer's clearance "regarding the completion of work from fire protection point of view" before the occupancy certificate (Reg. 2.10, p. 55).
03Who grants the clearance
The regulation says (Reg. 9.1, p. 144):
- 1For "plots upto 1000 sqm. having non-hazardous activities & buildings below 15 m height": any fire officer duly authorised by the CEO, examining the proposal "as per the guidelines and checklist given by fire department of MIDC".
- 2"For all other buildings": the Chief Fire Officer (CFO) of MIDC.
These powers are "subject to orders of the Authority from time to time". The CDCPR defines the Chief Fire Officer by reference to the Maharashtra Fire Prevention and Life Safety Measures Act, 2006 (Reg. 1.3(31), p. 21).
04Stage 1: the provisional fire NOC
The CDCPR itself does not use the words "provisional fire NOC". The term comes from MIDC's procedure document, which says:
- the application is one combined online submission through BPAMS, for building plan, provisional fire, temporary water connection and external drainage connection approvals;
- it is forwarded automatically to the "Concerned Fire Officer", scrutinised by AutoDCR software and verified by the fire officer;
- the architect certifies that the plans abide by MIDC's D.C. Rules and Parts 3 and 4 of NBC-2005 "wherever necessary";
- a demand letter is issued for Fire Protection Fund Fees, based on total built-up area and building height, and paid online;
- after scrutiny and payment, the provisional NOC is issued online for download.
Its document list (summarised in the factory guide linked above) centres on a process note, raw materials and finished goods with storage places marked on the block plan, and approvals from other bodies where your materials need them.
Fees. The document's fee table sets rates per sq. m with minimum amounts, varying by MIDC zone (A, B or C "under Group Scheme 1993"), building class, height and built-up area. Industrial buildings are split into low hazard (G-1), moderate hazard (G-2) and high hazard (G-3); storage (H) and hazardous (J) buildings have their own rows. Some taller categories in zones B and C are marked "Not Recommended". Because the document is undated, this guide does not quote its figures. The CDCPR says the Fire Protection Fund Fees "as applicable and amended from time to time" apply to all new developments in MIDC, under the Maharashtra Fire Prevention and Life Safety Measures Act, 2006, and that additional fees apply to all high-rise buildings (Reg. 9.13, pp. 158–159). Rely on the demand letter for your proposal.
05What the 2023 regulations ask you to design for
The fire officer's scrutiny is against these provisions. A selection of what matters most for factories and warehouses:
| Topic | What the regulation says | Regulation / page |
|---|---|---|
| Access for fire engines | Main street at least 12 m wide; margins of hard surface able to take a fire engine "weighing upto 45 tonnes", kept free and motorable; main entrance at least 6 m wide, with 4.5 m headroom if built over | Reg. 3.3.7, p. 65 (cl. (ii) cross-reference corrected to Reg. 2.2.8 (i) by the 2025 corrigendum, entry 22) |
| Height | Special buildings allowed up to any height "subject to approval of Chief Fire Officer", depending on fire-fighting capacity nearby | Reg. 5.9(i), p. 96 |
| Staircases | Special buildings to have two staircases, one a fire escape staircase of enclosed type | Reg. 8.29.7, p. 137 (as re-read by the 2025 corrigendum, entry 42) |
| Construction | Load-bearing elements, and elements needing one hour or more of fire resistance, to be of non-combustible material; main and fire escape staircases of RCC only | Reg. 9.2.1, p. 144 |
| Hazardous materials | None to be stored, handled, processed or manufactured in any part of a building 15 m or more in height | Reg. 9.4(i), p. 153 |
| Fixed systems | Extinguishers, hose reels, wet riser, yard hydrants, sprinklers and other systems "as applicable", sized as in Table 7 of NBC Part 4 | Reg. 9.6.1, p. 153 |
| Fire water | Static storage tank capacity as in Table 7 of NBC Part 4, in two or more interconnected compartments | Reg. 9.6.2.1, p. 154 |
| Detection and alarm | As per Table 7 of NBC Part 4; panel to monitor tank levels, hydrant and sprinkler pressures and pump status where an automatic system is provided | Reg. 9.7, pp. 157–158 |
| Fire control room | On the entrance floor, for residential buildings 30 m and above and all other buildings 15 m and above | Reg. 9.9, p. 158 |
| Industrial, storage, hazardous | Clauses 6.7, 6.8 and 6.9 of Part IV of NBC 2016 apply, and its Annexures A to M are to be referred to | Reg. 9.14, p. 159 |
| Compartmentation | For low and moderate hazard industrial buildings and storage buildings, to be done "in consultation with local fire department" | Reg. 9.15, p. 159 |
| Everything else | Planned "in accordance with" the Maharashtra Fire Prevention and Life Safety Measures Act, 2006, then NBC Part IV | Reg. 9.17, p. 160 |
Reg. 2.2.8 (pp. 45–46) also lists the fire details a special building's plans must show, such as the static water tank and pump room, the fire alarm network and fixed installations "as required by Chief Fire Officer, MIDC".
06Stage 2: the final fire NOC
The regulation says (Reg. 2.9, p. 54): for special buildings, the completion certificate "shall also be accompanied with the final fire NOC from Chief Fire Officer of the MIDC".
The regulation says (Reg. 2.10, p. 55): for special buildings, the occupancy certificate is issued "only after the clearance from the Chief Fire Officer of the MIDC, regarding the completion of work from fire protection point of view".
None of the sources listed with this article sets out the procedure, documents or fees for the final fire NOC. Ask MIDC's fire department for its current requirements before construction ends.
07After occupation: fire safety is a continuing duty
The regulation says (Reg. 2.15(ii), p. 57): a person who neglects obligations under the regulations, "including the maintenance of fire protection services, appliances and lifts in working order", is guilty of an offence under section 36 of the Maharashtra Fire Prevention and Life Safety Measures Act, 2006.
Regs. 9.11 and 9.12 (p. 158) add good housekeeping, fire notices at vantage points and regular training of occupants.
08Expanding or revising an existing building
The regulation says (Reg. 1.5(c), pp. 36–37, as amended by the 2025 corrigendum, entry 10): for buildings between 15 m and 24 m that comply with the special-building provisions, an NOC from the CFO "shall not be necessary" when applying for revised permission under the CDCPR. The corrigendum adds the words "except hazardous buildings".
Practical tip: for expansions, the provisional fire NOC document list asks for the existing MIDC certificates, approved drawings and a note on existing fire measures. Keep them filed.
09Checklist for your project
- 1Ask your architect to confirm, at concept stage, whether the building is a "special building" under Reg. 1.3(111)(xiv).
- 2Check Reg. 9.1: is your proposal for the authorised fire officer, or for MIDC's CFO?
- 3Fix your process, raw materials, finished goods, quantities and storage locations before drawings are frozen.
- 4Collect approvals from other bodies (explosives, MPCB, DISH, FDA) that your materials need.
- 5Design access, margins and the entrance gate for a fire engine as Reg. 3.3.7 describes.
- 6Keep hazardous materials out of any building 15 m or taller (Reg. 9.4(i)).
- 7Agree compartmentation with the fire department early if your building is low or moderate hazard industrial or storage (Reg. 9.15).
- 8Pay only the amount in the fire officer's demand letter.
- 9Before completion, ask MIDC's fire department what the final fire NOC needs.
- 10After occupation, keep fire systems maintained and staff trained.
Practical tip: leasing or buying a built shed? Ask the owner for the final fire NOC and the occupancy certificate, and bring in a fire consultant early: much of Chapter 9 points to NBC Part 4 tables that need a specialist.
10What the sources don't cover
- The final fire NOC procedure, documents and fees.
- A current, dated Fire Protection Fund fee schedule.
- MIDC's revised BPAMS workflow. The 13 January 2026 notice says BPAMS has incorporated the CDCPR and that a revision has begun, inviting suggestions within seven days; it does not describe the revised process. See the BPAMS revision notice.
- The text of the Maharashtra Fire Prevention and Life Safety Measures Act, 2006 and of NBC 2016, which Chapter 9 relies on.
- Any periodic fire certificates after occupation under the 2006 Act.
The regulations are on MIDC's site: CDCPR 2023 (Gazette), the 2025 corrigendum and the provisional fire NOC procedure.