01What this covers
Many manufacturers look at private land outside an MIDC industrial area. The first question is usually "can I build a factory here, and whose permission do I need?"
This guide answers that question only from the text of the Maharashtra Regional and Town Planning Act, 1966 (the MRTP Act), as published on India Code with the text as on 10 March 2025. Section numbers and page numbers below are as printed in that text.
It does not cover the building rules themselves. FSI, setbacks, road widths, heights and similar limits for land outside MIDC come from the development control regulations that apply to that land. This guide does not cover those regulations. It also does not cover permissions under other laws (for example land revenue, environment, factory or fire laws).
02Why location matters first
The MRTP Act works through plans. First find out which plan, and which authority, covers your land.
- Regional plan. A plan for the development of a Region, approved by the State Government and in operation under the Act (s. 2(25)). Under s. 14(a), a Regional plan may allocate land for different uses, including the extent to which land may be used as residential, industrial, agricultural or forest. Under s. 14(e), it may reserve sites for industrial estates and other large-scale development.
- Development plan. A plan for the development or re-development of the area within the jurisdiction of a Planning Authority (s. 2(9)). Under s. 22(a), it may allocate land for uses such as residential, industrial, commercial and agricultural. Under s. 22(g), it may designate sites for service industries and industrial estates.
- Planning Authority. A local authority, and includes a Special Planning Authority under s. 40 (s. 2(19)).
The Act says that land in an MIDC area is handled differently. Under s. 40(1A), an area where Chapter VI of the Maharashtra Industrial Development Act, 1961 applies, or Government land handed over to MIDC, is deemed a "notified area". MIDC is the Special Planning Authority for that area. On an MIDC plot, MIDC grants building permission under its own regulations. See building a factory on an MIDC plot and FSI and setbacks on MIDC plots.
Practical tip: before negotiating a price, get the zone of the land in writing from the plan that applies. A plot shown for agricultural or another non-industrial use may need a plan change, not just a building permission.
03What counts as "development"
The definition is wide. Under s. 2(7), "development" means carrying out building, engineering, mining or other operations in, over or under land. It also means making any material change in the use of any building or land. It includes demolition, reclamation, redevelopment, and lay-out and sub-division of land.
So both building works and a change of use of land, for example from agriculture to industry, are development under the Act.
04Who grants permission
Land in a Regional plan area
The Act says (s. 18(1)) that once the notice of a draft Regional plan, or of an approved Regional plan, has been published, no person may change the use of any land for any purpose other than agriculture, or carry out any development, without previous permission from:
- 1the Municipal Corporation, Municipal Council, Nagar Panchayat, Special Planning Authority or other planning authority, if the land is within its limits;
- 2the village panchayat concerned, if the land is in the gaothan; or
- 3the Collector of the District, if the land is in any other area. The Collector may delegate this power to an officer not below the rank of Tahsildar.
The Explanation to s. 18(1) says no Collector's permission is required in the gaothan area of a revenue village. Under s. 18(2), the village panchayat or Collector must have due regard to the draft or approved Regional plan when deciding an application.
Land in a Development plan area
The Act says (s. 43) that after the declaration of intention to prepare a Development plan is published, no person may institute or change the use of any land, or carry out any development, without the written permission of the Planning Authority. The same applies after a notification of a notified area or a new-town site is published.
s. 43 lists exceptions. These include internal works that do not materially affect the external appearance of a building, excavation (including wells) in ordinary agricultural operations, and a road giving access to land solely for agricultural purposes. None of the listed exceptions mentions building a factory.
Practical tip: the text does not tell you which plan covers a given survey number. Confirm with the authority concerned whether your land falls within a municipal or other planning authority's limits, a notified area, or a Regional plan area handled by the Collector.
05The application and the decision
| Question | What the MRTP Act says | Section |
|---|---|---|
| Who must apply? | Any person other than the Central or State Government or a local authority intending to carry out development, in writing, in the prescribed form with the prescribed documents. | s. 44(1) |
| What can the authority decide? | Grant unconditionally; grant with conditions imposed with the State Government's previous approval; or refuse. | s. 45(1) |
| What document is issued? | A commencement certificate in the prescribed form. | s. 45(2) |
| Must reasons be given? | Yes, for conditions imposed and for a refusal. | s. 45(3) |
| What must the authority consider? | Any draft or final plan or proposal published or sanctioned under the Act. Until DCRs for the area are sanctioned, the draft or sanctioned Regional plan. | s. 46 |
| What if there is no decision? | Permission is deemed granted if no decision is communicated within sixty days of the application, or of the applicant's reply to a requisition, whichever is later. | s. 45(5) |
| Is deemed permission always safe? | Only if the proposal strictly conforms to all relevant DCRs and does not violate any draft or final plan. Otherwise development under it is deemed unauthorised for ss. 52 to 57. | s. 45(5), provisos |
| Can I appeal? | Yes, against conditions or refusal, within forty days of communication, to the State Government or an officer not below Deputy Secretary. | s. 47(1) |
| How long does permission last? | One year from receipt of the grant. It may be extended year to year, but never beyond three years. | s. 48 |
| What if work is slow? | If work has not reached plinth level (or the top of the basement or stilt, where there is no plinth) within the year or extended period, a fresh permission is needed. | s. 48, second proviso |
| Can permission be revoked? | Yes, after a hearing, but not for building operations already carried out or substantially progressed, nor after a change of use has taken place. | s. 51(1) |
Practical tip: do not treat the sixty-day deemed permission as a shortcut. The Act ties it to strict compliance with the DCRs and plans, and the risk of getting that wrong sits with the owner.
If the plan does not allow industry
The Act provides for changing plans, but through a public process, not by application of a single owner. Under s. 37(1), a modification of a final Development plan is published in the Official Gazette, objections and suggestions are invited, affected persons are heard, and the proposal goes to the State Government for sanction. s. 20 provides for revision or modification of a Regional plan. This guide does not set out those procedures in detail.
06What happens without permission
The Act says:
- Offence (s. 52(1)). Developing or changing the use of land without the required permission, against its terms or conditions, or after it is revoked or modified, is punishable on conviction with imprisonment of not less than one month and up to three years, and a fine of not less than two thousand rupees and up to five thousand rupees. A continuing offence carries a further daily fine of up to two hundred rupees.
- Use against the plan (s. 52(2)). Continuing a use that contravenes a Development plan without being allowed under s. 45 or 47 is punishable with fine up to five thousand rupees, and up to one hundred rupees a day for a continuing offence.
- Removal (s. 53). Where development is without permission or after revocation, the Planning Authority may give 24 hours' notice to restore the land and, if the owner fails, take steps to demolish it and seal machinery and materials (s. 53(1)). Where development departs from a permission or a modified permission, the notice period is one month (s. 53(1A)).
- Stop work (s. 54). Development in progress can be ordered discontinued. Continuing after the notice is a separate offence.
- Temporary works (s. 55). Unauthorised temporary development can be ordered removed within fifteen days, then removed summarily.
- Expenses (s. 57). Expenses incurred by the Planning Authority under ss. 53 to 56 are recoverable from the person in default or the owner of the plot.
- Regional plan areas (s. 18(2A)). Sections 52 to 58 apply to unauthorised development in a Regional plan area, and the Collector is the competent authority to act.
Practical tip: if you are buying land or a shed outside MIDC, ask the seller for the commencement certificate and sanctioned plans. Under s. 45(6), the Planning Authority forwards authenticated copies of the certificate and sanctioned plans to the Collector within one month of issue.
07Checklist before you commit to land outside MIDC
- 1Identify which plan applies: a Regional plan, a draft or final Development plan, or a notified area (ss. 2(9), 2(25), 40, 43).
- 2Identify the authority: the municipal or other planning authority, the village panchayat for gaothan land, or the Collector for other Regional plan land (s. 18(1); s. 43).
- 3Get the zone or allocation of the land from that plan in writing (s. 14(a); s. 22(a)).
- 4If the land is not allocated for industry, find out whether a plan modification is possible and how long it may take, before paying (ss. 20, 37).
- 5Have your architect or engineer check the proposal against the development control regulations that apply to that land. This guide does not cover them.
- 6Apply in the prescribed form with the prescribed documents (s. 44(1)) and keep proof of the date of receipt and of any reply to requisitions (s. 45(5)).
- 7On grant, keep the commencement certificate and sanctioned plans, and diarise the one-year validity and the plinth-level requirement (ss. 45(2), 48).
- 8If conditions are imposed or permission is refused, note the forty-day appeal window (s. 47(1)).
- 9Check permissions under other laws separately. The MRTP Act is only one of them.
For the wider picture of locating and setting up a plant, see setting up a manufacturing unit.
"no person shall institute or change the use of any land or carry out any development of land without the permission in writing of the Planning Authority" (s. 43)